Garwood Cleaning & Lining Watermain Rehabilitation

J Fletcher employee working on New Jersey American Water Garwood Cleaning And Lining Project

PROJECT DETAILS

  • PROJECT NAME

    Garwood Cleaning & Lining Watermain Rehabilitation

  • LOCATION

    Garwood, NJ

  • PROJECT START AND END DATE

    1/7/19 – 12/31/19

SERVICES PROVIDED

• Cleaning and epoxy lining of 6-inch cast-iron water mains

• Replacement of 6-inch cast-iron water mains

• Replacement of existing water service lines

• Replacement of fire hydrants and valves

• Installation of temporary water bypass system to facilitate the cleaning and lining of existing CI pipes

QUICK STATS

  • Quick Stats

    • Cleaning and lining of 12,097 feet of 6-inch cast iron pipe (CIP)

    • Replacement of 365 water service lines

    • Installation of 26,000 feet of 4-inch and 2-inch bypass piping

    • Replacement of 3,100 linear feet of 6-inch cast iron water mains