Client: PSE&G
Services: Heavy Construction, Utility Construction

In 2013 J. Fletcher Creamer & Son, Inc. (Creamer) contracted with PSE&G to construct 14 tower foundations in the Delaware Water Gap National Park located in the Kittatinny Mountains of northwest New...

Client: -
Services: Guide Rail

Creamer contracted with the Virginia DOT to replace and / or install new guide rail throughout the State. Covering 174 sites and installing 41,000 LF of guide rail Creamer crews had their work cut out for them in...

Client: -
Services: Emergency

On June 30, 2012,  a timber pile supported pipe bridge collapsed in Tinton Falls New Jersey.  This pipe bridge was responsible for carrying the 42" raw water intake line from the adjacent reservior to the water...

Client: -
Services: Renewable Energy, Specialty Equipment

Performing solar installations can be a relativly simple task. Creamer found one project that others did not want to touch given the circumstances of the construction. This project was installed in a mountainous...

Client: Washington Suburban Sanitary Commission
Services: Utility Construction

 

Creamer contracted with Washington Suburban Sanitary Commission (WSSC) to install new water mains in Capital Heights, Maryland. In order to accomplish this task bypass pipe was used to allow service to...

Client: Middlesex Water Company
Services: Emergency

When an 8” blow off on a 60” transmission main was damaged J. Fletcher Creamer & Son was called into action. The existing 60” main, with a capacity of 19 million gallons a day, needed to be shutdown in order...

Client: -
Services: Sign Structure

 

This project included the inistallation of poles, signals and conduit to upgrade an intersection that is in close proximity to a school zone. The design of this project is specifcally to assist with...

Client: City of Hackensack
Services: Heavy Construction

The replacement of the Court Street Bridge, built in 1908, began in 2010. The Joint Venture of Creamer / Sanzari JV accomplished the task of removing the superstructure of the swing bridge that would be...

Client: PSE&G
Services: Utility Construction

In September 2012, Creamer completed the construction of a new substation in Camden, NJ. The substation, built to add redundancy and reliability in the area, would later house 5 new transformers and a new control...